The Connswater Community Greenway makes consistent progress across most works fronts in east Belfast.

In section D5, Sydenham Bypass to Mersey Street our contractor, Farrans Construction have finished piling works on both sides of the Connswater River and have begun the installation of a reinforced flood wall.


(Installation of the reinforced flood wall at section D5, Mersey Street to Sydenham Bypass)

Downstream in section D4, Mersey Street to Ballymacarrett Walkway Farrans have begun breaking piles in advance of works on a flood wall. In section D3 at the Holywood Arches Farrans continue work on the new event space for C. S. Lewis Civic Square, with the placement of large granite tiles.

In section D1, Connswater Link to Beersbridge Road, Farrans have installed a piling platform and have begun piling works in Bloomfield Industrial Estate

Further along the scheme in section C6, Beersbridge Road to Elmgrove our contractor has continued to make good progress  with the continued construction of a retaining wall and the beginning of concreting works on the CCG pathway.

In Section C7: Orangefield Park to Knock Dual Carriageway final concreting works are complete, landscaping works have begun and the area has been transformed looking more and more complete each day. Works on the Braniel are also due to begin soon.

Elsewhere, Farrans have begun works in section B2, Ladas Drive to Montgomery Road with the installation of a Readyrock Wall at the Belfast Metropolitan College. They have also begun works in section B6: Castlereagh Road to Ladas Way with the removal of fencing in private property and the installation of a haul road and site compound.

On the road sections of the Connswater Community Greenway Farrans continue to progress well at section A3, Cregagh Road and B9. Farrans are working to a planned schedule and hope to have works complete on Orby Road, before moving onto Orby Link soon. Farrans also plan to enter section A4 at Montgomery Road soon to continue the kerbing and resurfacing works for the scheme.

You can explore all the designs for the sections of the Connswater Community Greenway using the Explore the Greenway map tool on the home page of the CCG website. If you have any questions, queries or comments on our construction works please telephone Farrans Free Customer Care Line on 0800 0838 160.