Draft Programme

 

Please note this is a draft programme and is subject to change. 

The Rivers Agency Stand Alone works schedule for the East Belfast Flood Alleviation Scheme (EBFAS) is as below:

EBFAS section Completion Date
Castlereagh Rd Flood Defences  Complete
Montgomery Rd Complete
Grand Parade  Completion envisaged Dec 2015 / early Jan 2015
Castlereagh Road Culvert  Current to  Aug 2015 – Crossing of Catslereagh Road to commence around April 15
Clara Park Culvert Start Feb – early/mid summer 2015
Clara Park Flood Defences  Early/mid summer 2015 to Nov/Dec 2015
Ladas way Revised scope and Programme TBC