Draft Programme

Section Location  Start Finish
C3 (Phase 1) Orangefield Park  Apr 13 Oct 14
D6 (Phase 1) Victoria Park May 13 Oct 14

A1, A2, A3, & A4

(Phase 2)

Cregagh Glen, Upper Knockbreda Road, Cregagh Road and Montgomery Road TBC TBC
D3 (Phase 2) Holywood Arches TBC TBC
B2 (Phase 2) Loop River - Mongomery Road to Lada Drive TBC TBC
B4 & B6 (Phase 2) Loop River - Ladas Drive to Ladas Way & Ladas Way to Castlereagh Road TBC TBC
D1 (Phase 2) Beersbridge Road to Connswater Link Bridge TBC TBC
D2 (Phase 2) Connswater Link Bridge to Newtownards Road TBC TBC
B9, C5 & C6 (Phase 2) Orby Link, Dixon Park & Elmgrove TBC TBC
C7 (Phase 2) Orangefield Park to Knock Dual Carraigeway TBC TBC
D4 & D5 (Phase 2) Newtownards Road to Mersey Street, Mersey Street to Sydenham By-Pass TBC TBC
       
Rivers Agency      
     
B3 Ladas Drive Culvert Jan 14 Feb 15
B7 Castlereagh Road Culvert Jul 14 Jan 15
B5 Ladas Way Culvert Jan 14 Feb 15
C4 Grand Parade Culvert Mar 14 Oct 14
B1 Montgomery Road Culvert Apr 14 Aug 14
C1 & C2 Clara Park Flood Defence Wall Jul 15 Nov 15

The programme of works for Phase 2 works should be confirmed by November 2014. Please check back for details or subscribe to our mailing list. 

Please note this is a draft programme and is subject to change. 

You can download a map of the Rivers Agency Stand along works below.

DocumentSize
Rivers Agency Stand Alone Works97.38 KB